century sign3crossrinityLutheran Church
1553 Kinney Ave., Mt. Healthy, OH 45231 • 513.522.3026
  24 hour information line:  513.522.8515          letterClick Here to Email Trinity
 
 
Work started on our new Narthex & Office addition in early June, 2007. Construction delays (planned and unplanned) have caused us to revise the expected completion date.  We're now anticipating completion before summer 2008.  Check this page often for new developments and the latest photos.

Check the links below for slideshows of the varying stages of progress.
April 2008   - Brick work is complete, roofing is in process, and interior work has begun.  The design team is investigating costs for furnishing the new space and for landscaping the prayer garden.  Check the latest photo slideshow for an inside view!!

March 2008
- Although delayed by snow and rain, constupdate1the exterior is taking shape.  The brick is being put on and other interior work is continuing.  Once the brick work is complete, the roof will be put on.  When the roof is on, weather delays will be minimized.  Nearly all of the interior design choices have been finalized.




February 8, 2008 -  Work is progressing as steel framing is put up and you can see walls with locations where windows will be.  The structure is definitely taking shape. 

January 7, 2008 - The crane returned with the steel framework for the walls of the addition.  The grading in front of the addition has been started, and the prayer garden has been filled in to make it level with the addition floor.  The latest photos are below.

November 19 2007 - A crane arrived, steel arrived, and workers began connecting the steel to the existing foundation and welding the steel in place.  Latest photos are shown below.crane

November 2007 - The Architect, Contractor and members of the Leadership group met in early November to iron out differences and to work out a new planned schedule.  There will be regular communication among all parties so we can keep the project moving.  Structural steel is to be delivered the first week of November, with major construction tasks beginning the second week of November.  Weather may cause delays at this point, and further fine-tuning of the plans may be needed.  Look for new slideshows once the next construction steps begin.

September 2007 - Foundation is poured, connecting openings to the existing building are cut, elevator shaft is going up, base is being leveled, progress continues!  Check out the slideshows!!

August 2007
The former Clara’s Corner lot is now a huge pile of dirt, the big dig is completed and the footers have been poured!  After this quick start, the project stalled in the past weeks because the drawings completed by the architect and those done by the structural engineer have some discrepancy. Before the const 3contractor will proceed with pouring the foundation this must be rectified.  It is anticipated this will be done quickly and construction will resume.  The project is still slated to be completed by the end of October as delays of this nature are not unexpected. A decision has been made to complete the prayer garden at this time with the money for this coming from some of the funds bequeathed to Trinity by Ruth Hust.  Thanks to her generosity we will have a quiet place to pray and reflect. It is not too soon to begin thinking about how we will put our new narthex to use.  Also, we will eventually complete the new church offices in the addition.  This will free up the space where the office is now located.  Gary Fredensborg is putting together a working group to plan for space usage (both our new space and that which now exists.)  If you would like to serve on this group, please let Gary know of your interest. Here is a quick update on the finances of the project.  The approximate cost is $850,000.  The congregation has generously pledged $650,000 through the three-year capital campaign.  As of the end of June, 2007 members have contributed $340,000.  Please continue to make your contributions as you are prayerfully able.  
 
chart

   
  PROJECT BEGINNINGS:
June 25 2007 - Excavation of the foundation has begun.  They uncovered two old cisterns and some of the foundation from an old church building.  Cement will be poured in early July.  Permits are expected from Mt. Healthy zoning within days, and work on the building will start once the foundation is ready.  The design team has reviewed elevator designs and considered carpeting styles.

June 2007 - The builder (Century Construction) and key members of the building Leadership group met on site to discuss the planned work.  The builder expects to begin the foundation work on June 11.  The remaining 33 drawings will be completed and submitted for zoning approval soon.  A separate contract has been signed and workers have been directed to begin the final leveling of the Clara's corner property prior as soon as possible.J

May 2007 - The foundation plans have been completed and Mt. Healthy is reviewing them so construction of foundation can begin.  Drawings on the building are still being fine tuned and prepared for final approval.  There are over 20 drawings involved. 


March 2007 - We are finalizing a contract with Century Construction.  The Design team continues to meet to work out various details.  A groundbreaking is planned for April 1.


 ----- ----- ------ ------2006 ---- ----- ----- -----
October - The leadership group, builder, and architect met to discuss the next steps.  A letter of intent was signed so initial steps could be taken until the formal contract could be reviewed and approved.  At this point the builder is proceeding with preliminary work as we wait for the final contract approval.

September 10 - The congregation met and voted on the plans.  The vote was 57 to 10 (& 2 abstensions) in favor of building the addition as described in the August revised plans presented at the meeting. 

August - The architect has completed a revised design and a builder has provided estimated costs.  We have announced a congregational meeting for September 10th following the 11:15 am service.  Please plan to attend this important meeting!
July - The architect is reviewing the design to determine how to reduce costs and still provide a building that meets our needs.  The design team is working in tandem with the architect for the next few weeks until they cao offer a recommendation to the Building project leadership team..

May 21 - The congregation met to review estimated costs that have been established for the project.  Costs are more than 50% higher than expected, so the design team will review all costs and plans to determine how to meet our budget.  This process will take 6 to 8 weeks.

March 21 - The leadership team met to consider how to proceed with our project in light of Tim's departure in April.  We agreed to continue with design and cost estimates, then to present this to the congregation for approval in May.
March 6 - The design team is currently studying three alternative plans to determine which will best meet our needs within our budget.  Meetings are planned for March 7th and 21st.  The Leadership team will also meet on the 21st to evaluate overall progress.
February 15 - With the help of architect Bryon Southerly, in recent weeks the Steering Committee has focused on developing a set of conceptual plans for the addition. These plans provide us a basic look at how the space will be arranged. The plans are by no means complete at this time, but the main elements include new office space, open space for gathering before/after worship or other events, an interior garden area, new, handicapped accessible restrooms, and an elevator to provide easier access to the lower level.  The lower level of the addition will be unfinished.

January 2006 -
A Steering Team has been formed to manage the process of design and oversight of the new Narthex/Office Addition. The committee is being led by John Wendt and meets the first Tuesday of each month. Team members are: Terri Bax, Jerry Larson, Carl Greber, Gary Fredensborg, Dave Miller, and Nancy Tolford-Peeno.  Also, three sub-committees have been formed for design, building, and financing:
   
Narthex Addition Construction Progress Page
model
 

Construction Team--responsible for oversight of the construction phase.

Carl Greber, Chair
Dave Stenger
Jim Drake
We also have a Financial Team, a Design Team, and an overall Project Leadership Team.
 
The Builder / General Contractor is Century Construction

SLIDESHOWS
  Week 1 April 2008 
Week 3 March 2008 
Week 1 February 2008 
Week 1 January 2008
Crane arrives and steel work begins
Interior Shots, Courtesy of Charlie Webb
The Elevator shaft is started 
Work Continues in September - Foundation! 
Progress mid August 2007
Work continues in August:
July Progress
More progress in late June
Work Begins June 2007

 const1

const2

const 5

const 4

ELCA


page updated 4/03/08